Refineries of South Pars phases 22&24

Refineries of South Pars phases 22&24

Refineries of South Pars phases 22&24

Azmoon Felez Pars Company in the 22nd and 24th Phase Refinery Project since 2016 is now proud to partner with Techno Energy Sepehr Kish (Tesco), with a contract volume of 628,000 inches (950 test packages).

These projects are in the areas of piping, mechanical, civil, paint and insulation of units 100-1, 100-2, 103-1, 103-2, 110, 130, 181, ۱۶۰ and PIG RECEIVER.

Geolocation of the project

IRAN – Bushehr Province – Kangan City – PHASES 22,23,24

Activity description

contract number : TES-SP-C-AZP-95-1263, TES-SP-C-AZP-2224-95-1289

Project start time : 2016/06/30

Project Duration : 6 Month

Relative Units: 100-1, 100-2, 103-1, 103-2, 110, 130, 181, ۱۶۰ and PIG RECEIVER.

Scope of activity and project work scopes : Piping, Mechanical, Civil and Paint & Insulation.

Project Specifications and Area of Activity

Primary Employer: POGC

Employer :TESCO(Techno Energy Sepehr Kish Co)

Contractor : AFP (Azmoon Felez Pars Co)