Performing Operations of Hook-UP and Assist the commissioning and Startup in the Section of Piping, Mechanical, HVAC, structure, Paint, Insulation, Scaffolding, Electrical and Instrumentation.
And Also Doing Activities of Pre-commissioning, Doing the rest of the work in the sea, Supply of Equipment on South Pars Platform 13B and Also Eaintenance of Equipment and Installations(Preservation).
IRAN – Bushehr Province – Bushehr City – Sadra Island
contract number : S-TES-C-AFP-97-585
Project start time : 2017/07/06
Project Duration : 6 Month
Scope of activity and project work scopes : Piping, Mechanical, HVAC, structure, Paint, Insulation, Scaffolding, Electrical and Instrumentation and communication
Project Stakeholders : POGC and SADRA
Project owner : POGC (Pars Oil And Gas Company)
The main employer : SADRA
Consultant : Germanischer Lloyd ,Germany’s Company
Contractor : AFP (Azmoon Felez Pars Co)
Projects’s Pictures